Wastewater Treatment (STP) Calculator

The Wastewater Treatment (STP) Calculator finds the design flow, BOD load, and aeration tank volume for a sewage treatment plant. Example: for a 500-person facility at 120 L/person/day, BOD 250→30 mg/L, Design flow = 60 m³/day, BOD removal = 88 %, Aeration volume = 17.9 m³ (per DENR DAO 2016-08).

How it works

Computed from your inputs per DENR DAO 2016-08.

Worked example (Plumbing & Pumps)

Inputs: a 500-person facility at 120 L/person/day, BOD 250→30 mg/L.

ResultValue
Design flow60 m³/day
BOD removal88 %
Aeration volume17.9 m³

Computed live by WorkHive's calculation engine; standard: DENR DAO 2016-08.

How to use this calculator

  1. Enter the figures for the duty you are sizing: the worked example below uses a 500-person facility at 120 L/person/day, BOD 250→30 mg/L.
  2. The calculator returns Design flow, BOD removal, Aeration volume, computed per DENR DAO 2016-08.
  3. Check the worked example to confirm the method matches how you would do it by hand, then run your own numbers in the interactive tool.

FAQ

What is a sewage treatment plant sizing calculator BOD?

The Wastewater Treatment (STP) Calculator is a free online tool that computes finds the design flow, BOD load, and aeration tank volume for a sewage treatment plant. It shows the formula and a fully worked example so you can check the method, not just the number.

How is it calculated?

The result is computed from your inputs following DENR DAO 2016-08. The worked example on this page shows a real computation with real numbers.

Is the calculator free?

Yes. WorkHive's engineering calculators are free to use, no sign-up needed for the tools. WorkHive is a free, offline-first maintenance platform built for Philippine industrial plants.

Run it on your own numbers

Open the interactive Wastewater Treatment (STP) Calculator in WorkHive: free, no sign-up needed for the calculators.